Beyond the audits
The losses reported outside the Auditor-General’s books.
Contracts, procurements and programmes where a specific figure has been documented by a parliamentary committee, a state-commissioned audit, a court, or a major investigation. These figures are not part of the Auditor-General totals shown elsewhere on this site, and are never added to them.
- 2009–2017
- 2017–2025
- 2025–present
Total shown$6.73B
- Documented in this selection
- $6.73B
- Cases
- 21
- Years covered
- 2013–2026
These figures come from different bodies using different methods, and mix contract values, queried sums and reported losses. The total is a sum of separately-reported figures — it is not one audited number, and it should not be read as a single verified loss to the state.
The largest documented figures
Each bar is one case, coloured by the governing period the contract or spending falls in. Select a bar to open the record and its sources.
Bars mix figure types. Read the label on each record before comparing them.
SourceParliamentary committee reports, state-commissioned audits, court records and named investigations
By year first reported
Grouped by the year the figure entered the public record, not the year the spending occurred.
Columns are coloured by the government in office in that reporting year, which is not always the government under which the spending occurred.
SourceAs cited on each record below
By sector
Where the documented figures concentrate across the current selection.
SourceAs cited on each record below
By governing period
Records are grouped by the governing period in which the contract or spending falls. This is an indexing decision and says nothing about responsibility.
- 2009–20174 cases$31,637,368
- 2017–202512 cases$4,771,661,910
- 2025–present5 cases$1,930,670,741
Case counts differ sharply between periods, so totals here are not a like-for-like comparison.
SourceAs cited on each record below
The records
Case by case
Expand any record to read the summary, the figure type, any dispute over the number, and every source behind it.
- Cocobod cocoa roads contracts$1.51B
2025–present· Agriculture · reported 2026
Amount queriedModerate78Source reliability 78 out of 100, Moderate sourcing. 2 newsroom · 2/2 dated. Citation completeness 100%. - GIIF Sky Train project$2M
2025–present· Transport · reported 2025
Reported lossModerate78Source reliability 78 out of 100, Moderate sourcing. 2 newsroom · 2/2 dated. Citation completeness 100%. - National Cathedral project$400M
2025–present· Construction · reported 2025
Documented estimateModerate78Source reliability 78 out of 100, Moderate sourcing. 2 newsroom · 2/2 dated. Citation completeness 100%. - SML revenue assurance contract$19.58M
2025–present· Revenue assurance · reported 2025
Amount queriedStrong92Source reliability 92 out of 100, Strong sourcing. 1 official · 1 newsroom · 2/2 dated. Citation completeness 100%. - Akonta Mining forest reserve case—
2025–present· Mining · reported 2025
Reported lossModerate70Source reliability 70 out of 100, Moderate sourcing. 2 newsroom · 2/2 dated. Citation completeness 80%. - Ambulance spare-parts payment$34.9M
2017–2025· Health · reported 2024
Amount queriedModerate78Source reliability 78 out of 100, Moderate sourcing. 2 newsroom · 2/2 dated. Citation completeness 100%. - COVID-19 expenditure queries$63.29M
2017–2025· Health · reported 2023
Amount queriedModerate78Source reliability 78 out of 100, Moderate sourcing. 2 newsroom · 2/2 dated. Citation completeness 100%. - Airbus SE bribery findings$5M
2017–2025· Procurement · reported 2020
Reported lossStrong100Source reliability 100 out of 100, Strong sourcing. 2 official · 2/2 dated. Citation completeness 100%. - GPGC power purchase judgment debt$170M
2017–2025· Energy · reported 2019
Reported lossModerate78Source reliability 78 out of 100, Moderate sourcing. 2 newsroom · 2/2 dated. Citation completeness 100%. - PDS / ECG concession termination$190M
2017–2025· Energy · reported 2019
Reported lossModerate78Source reliability 78 out of 100, Moderate sourcing. 2 newsroom · 2/2 dated. Citation completeness 100%. - Banking sector clean-up cost$3.8B
2017–2025· Finance · reported 2019
Reported lossModerate78Source reliability 78 out of 100, Moderate sourcing. 2 newsroom · 2/2 dated. Citation completeness 100%. - Saglemi affordable housing project$200M
2017–2025· Housing · reported 2019
Reported lossModerate78Source reliability 78 out of 100, Moderate sourcing. 2 newsroom · 2/2 dated. Citation completeness 100%. - Cash-for-seat / Ghana Expatriates Business Awards—
2017–2025· Procurement · reported 2018
Amount queriedModerate58Source reliability 58 out of 100, Moderate sourcing. 1 newsroom · 1/1 dated. Citation completeness 80%. - Kelni GVG telecom monitoring contract$89M
2017–2025· Telecoms · reported 2018
Contract valueModerate78Source reliability 78 out of 100, Moderate sourcing. 2 newsroom · 2/2 dated. Citation completeness 100%. - SSNIT Operational Business Suite$72M
2017–2025· Procurement · reported 2017
Amount queriedModerate66Source reliability 66 out of 100, Moderate sourcing. 1 newsroom · 1/1 dated. Citation completeness 100%. - BOST contaminated fuel sale—
2017–2025· Energy · reported 2017
Amount queriedModerate70Source reliability 70 out of 100, Moderate sourcing. 2 newsroom · 2/2 dated. Citation completeness 80%. - AMERI power agreement overpricing$150M
2017–2025· Energy · reported 2017
Amount queriedModerate78Source reliability 78 out of 100, Moderate sourcing. 2 newsroom · 2/2 dated. Citation completeness 100%. - Metro Mass bus branding contract$949.87K
2009–2017· Transport · reported 2015
Contract valueModerate78Source reliability 78 out of 100, Moderate sourcing. 2 newsroom · 2/2 dated. Citation completeness 100%. - Woyome judgment debt$16M
2009–2017· Finance · reported 2014
Reported lossModerate78Source reliability 78 out of 100, Moderate sourcing. 2 newsroom · 2/2 dated. Citation completeness 100%. - SADA guinea fowl and afforestation contracts$14.69M
2009–2017· Agriculture · reported 2014
Amount queriedModerate78Source reliability 78 out of 100, Moderate sourcing. 2 newsroom · 2/2 dated. Citation completeness 100%. - GYEEDA youth employment contracts—
2009–2017· Social programmes · reported 2013
Amount queriedModerate70Source reliability 70 out of 100, Moderate sourcing. 2 newsroom · 2/2 dated. Citation completeness 80%.
Methodology
What qualifies, and what does not.
A case appears here only when a specific figure has been published by a parliamentary committee, a state-commissioned audit, a court or prosecutorial filing, an official statement, or a named investigation by an established outlet. Where we could not tie a case to a published figure, it is left out rather than estimated.
Every record states what its number actually is: Contract value (The value of the deal itself — not a loss finding.); Amount queried (A sum a committee, auditor or investigator formally questioned.); Reported loss (A loss stated by an official body or court record.); Documented estimate (A documented estimate published by a named source.). A contract value is not a loss, and a queried amount is not a proven one.
Each record carries a source reliability score out of 100 and a citation completeness bar. The score is mechanical: it rewards an official source (prosecutor, court, auditor, parliament), corroboration by more than one named publisher, publication dates on every citation, and a specific amount tied to a currency year. It measures how well a figure is documented — never whether the underlying claim is true.
These figures are kept strictly separate from the Auditor-General dataset. The two are produced by different bodies on different bases, and some sums may overlap with audit findings — adding them together would double count.
Cedi and dollar figures are the amounts as reported, converted at the exchange rate for the year the figure was reported. No inflation adjustment is applied, so amounts from different years are not directly comparable.
Attribution is by the government in office at the time of the contract or spending, not the government in office when the figure surfaced. It is a filing convention, not a finding of responsibility, and nothing here is a determination of guilt. If a figure is wrong or out of date, report it and we will re-check the source.